Home Planning & Development Building Building Inspection & Permits Seismic Requirements in the CVRD
All new and substantially reconstructed buildings in the CVRD are required to comply with the BC Building Code (BCBC) 2024 seismic requirements that were delayed from March 2024. Plans for proposed buildings must show compliance with the 2024 BCBC, and must show detailed Braced Wall Band and Panel design and calculations (bands, panels, and wall framing reference types must be shown, and calculations under the Part 9 must be provided). Building Permit Applications submitted with plans without clear Braced Wall Band and Panel designs and calculations will be rejected and a building permit cannot be issued until compliant seismic design and detail is provided and reviewed by CVRD Building Inspection staff, or Part 4 design (Structural Engineering) may be required.
If the building meets all of the following criteria, Part 9 seismic compliance can be presented to the CVRD Building Inspector for review with your Building Permit Application:
No. The 2024 BCBC requires Braced Wall Bands and Panels under Part 9 design. A post and beam structure requires design and oversight by a Registered Professional under Part 4 of the 2024 BCBC.
No. Under the 2018 BCBC, there was an exemption for single storey residential Accessory Buildings that met certain criteria. The 2024 BCBC does not provide that exemption unless a Geotechnical Engineer has determined your Site Class, and your Smax has been calculated to be below 1.2.
Please note that under the new 2024 BCBC seismic provisions, the “Additional System Considerations” are no longer permitted in areas with an Smax over 1.2. Single storey accessory buildings, garage front wall, porch roof, etc. exemptions are no longer available unless the Smax is below 1.2. ALL Electoral Areas within the CVRD have an Smax over 1.2 (at Site Class C), however, Smax may be determined by a Professional Geotechnical Engineer and may be lower than 1.2, however, this is not guaranteed, and is site and soil specific.
Due to the Smax values in the CVRD, only the Part 9 Calculation Method or the Alternative Calculation Method may be used (Simplified Method is not permitted).
Part 9 Seismic Designs must clearly illustrate ALL of the following:
Part 4 Structural Design is under Division B Acceptable Solutions of the BC Building Code where Article 2.2.1.2 Structural Design states “For design carried out in accordance with Part 4 of Division B, the designer shall be a registered professional skilled in the work concerned.”
This involves having the building designed and reviewed per the requirements of Part 4 Structural Design of the 2024 BCBC by a registered professional (usually a structural engineer) instead of the prescriptive requirements of Part 9. This requires that an engineer be retained for the project who will provide sealed structural drawings accompanied by a Letter of Assurance (Schedule B) for your building permit application.
This option provides significantly greater flexibility in building design than the Part 9 requirements (such as post and beam connections, tall walls/high ceilings, designs beyond ‘repetitive framing members,’ large openings/glazing, and more).
The structural engineer then performs Field Reviews to inspect the construction of the building and confirm that it is being constructed per their design and specifications. At the end of the project and when they have confirmed the final building meets all of their design and specification requirements, the engineer will provide a final Letter of Assurance (Schedule C-B) which is required for Final inspection/Occupancy.
Building Permit Applications where a registered professional has provided a sealed design and Letter of Assurance may be subject to a discount on permit fees per section 743 of the Local Government Act.